How to add your knowledge

Drawing List Report

    Table of contents
    No headers

    Procedures:

    Drawing List Report

    Reports the settings of each drawing in the project, and provides the means to edit the report and update the drawing properties with the edited values.

    1. Click Project tab ac.menuaro.gif Project Tools panel ac.menuaro.gif Manager.icon_cmd_ace_proj.png
    2. In the Project Manager, right-click the project name, and select Drawing List Report.
    3. (Optional) In the Drawing List Report dialog box, click Format and browse to a report format file.
    4. Click New Report.
    5. Select the drawings to process.
    6. Click OK.

      The data is displayed in the Report Generator dialog box so you can change the report format, save to a file, and place the report as a table.