How to add your knowledge

Marking a Task Complete

    You can mark a task as “Complete” from several different locations in Constructware. You can only mark a task as “Complete” if you have accepted the task.

    Personal Tasks or Project Tasks

    To mark a task complete from Personal Tasks or Project Tasks:

    1. Navigate to: Personal OrganizerPersonal Task or Project OrganizerProject Tasks.
    2. Select the Task you want to mark “Complete”.
    3. Click Mark Complete.
      • The Task Owner is notified of your Task Completion if they selected the Notify me when the Task is Complete checkbox when they assigned or created the task.
      • The Task Creator may be notified of your Project Task completion, based on the setting in Module Customizations.

    CW Desktop - Today Page

    To mark a task complete from the Today page:

    1. Navigate to: CW DesktopToday Page.
    2. Select the Task you want to mark complete.
    3. Click Take Action.
    4. Select Mark Complete from the fly-out menu.