Connect compatible air terminals and air handling equipment to provide the heating and cooling required for the project.
Add air terminals and air handling equipment. | ![]() | Use the Heading and Cooling Loads report to determine the capacity for air terminals and equipment. Place air terminals and air handling equipment in the plan. |
![]() | ||
![]() | Assign grills, air terminals and air handling equipment to supply, return, and exhaust systems. | |
![]() | ||
![]() | Use Generate Layout tools to create and route ductwork connecting your air terminals and air handlers. | |
![]() | ||
![]() | Change the routing and manually adjust ductwork to avoid obstructions. | |
![]() | ||
![]() | If necessary, justify sections of ductwork. | |
![]() | ||
![]() | Revit MEP sizing tools let you automatically specify duct sizes that provide the correct flow throughout your systems. | |
![]() | ||
Create groups and copy them to other areas in the project. (optional) | ![]() | You can create groups of components to replicate similar systems in other spaces or on other levels. |
![]() | ||
![]() | Check the connectivity throughout your systems. | |
![]() | ||
![]() | Use the system inspector to verify flows. | |