How to add your knowledge

Creating a Schedule or Quantity

    Table of contents
    No headers
    1. Click Manage tabViews panelSchedules drop-down Schedule/Quantities.
    2. In the New Schedule dialog, select a component from the category list. A default name appears in the Name text box, which you can change as necessary.
    3. Select Schedule building components.
      NoteDo not select Schedule keys. If you want to create a key schedule, see Key Schedules.
    4. Specify the phase.
    5. Click OK.
    6. In the Schedule Properties dialog, specify the schedule properties. See Specifying Schedule Properties.
    7. Click OK.